马来西亚东海岸铁路一期启动试运行:鹅唛至哥打巴鲁全程不到4小时、目标12月12日通车

2026-11-07 · 世界 · GSM News
马来西亚东海岸铁路一期启动试运行:鹅唛至哥打巴鲁全程不到4小时、目标12月12日通车

吉隆坡 — 马来西亚东海岸铁路(ECRL)11月7日启动试运行,这是该线路在12月12日目标通车日期前最后的运营准备阶段。项目业主 Malaysia Rail Link(MRL)当天发表声明宣布了这一安排。

试运行由 MRL 与中国交通建设(ECRL)有限公司各持股五成的 ECRL Operation 公司负责,11月7日至12月2日进行。列车在雪兰莪州鹅唛(Gombak)与吉兰丹州哥打巴鲁(Kota Bharu)之间双向运行,涵盖直达与停站两种服务,并按计划中的商业时刻表运行、配发登车牌并提供客舱服务,以检验运营就绪程度、服务效率、车站管理与乘客体验。

试运行首班车当天上午7时整从鹅唛综合交通枢纽站发车,上午8时28分抵达彭亨州关丹的 KotaSAS 站,载有170名乘客,最高时速160公里;继续开往哥打巴鲁的列车于上午10时58分抵达,全程不到4小时。

MRL 表示,试运行在系统集成测试完成、无故障运行测试于10月29日成功完成之后进行。截至2026年10月,哥打巴鲁至鹅唛的一期工程建设进度为98.47%。一期线路设16个车站,票务与乘客服务的进一步信息将于11月中旬公布;鹅唛至巴生港的二期工程计划2027年12月完工、2028年1月投入运营。

(来源:马来西亚国家新闻社)

Malaysia's East Coast Rail Link Starts Trial Operations: Gombak to Kota Bharu in Under Four Hours, With Launch Targeted for December 12

KUALA LUMPUR — Malaysia's East Coast Rail Link (ECRL) began trial operations on November 7, the final stage of operational readiness before commercial passenger services targeted to begin on December 12. Project owner Malaysia Rail Link (MRL) announced the programme in a statement that day.

The trial operations, running from November 7 to December 2, are conducted by ECRL Operation Sdn Bhd, a 50:50 joint venture between MRL and China Communications Construction (ECRL) Sdn Bhd. Trains run in both directions between Gombak in Selangor and Kota Bharu in Kelantan, providing express and stopping services to the planned commercial timetable, with boarding passes issued and cabin crew services provided, to assess operational readiness, service efficiency, station management and the passenger experience.

The first train departed the Terminal Bersepadu Gombak station at 7:00 a.m. sharp and arrived at KotaSAS station in Kuantan, Pahang, at 8:28 a.m., carrying 170 passengers at speeds of up to 160 km/h. The train continued to Kota Bharu, arriving at 10:58 a.m., a journey of under four hours.

MRL said the trial follows completion of system integration testing and a successful fault-free run on October 29. As of October 2026, construction of Phase 1, the Kota Bharu-Gombak alignment, had reached 98.47%. Phase 1 has 16 stations, and further information on ticket sales and passenger services will be announced in mid-November. Phase 2, from Gombak to Port Klang, is scheduled for completion in December 2027, with operations expected from January 2028.

(Source: Bernama)

来源:马来西亚国家新闻社

发布:GSM·美国(发布链接)

图片来源:图:马来西亚东海岸铁路的 EMU-001 动车组(资料图)。kaya-yu 摄,CC BY 4.0,经 Wikimedia Commons。 / Photo: An ECRL EMU-001 trainset (file photo). By kaya-yu, CC BY 4.0, via Wikimedia Commons.

GSM Global · 本篇英文版 English edition of this story