北卡罗来纳州S线铁路获5.5亿美元联邦资金:罗利至里士满走廊设计时速110英里

北卡罗来纳州韦克县罗利市,美国联邦铁路管理局一笔5.5亿美元的拨款正推动S线铁路项目建设:这条连接北卡罗来纳州罗利市与弗吉尼亚州里士满市的客运铁路走廊全长约162英里,设计时速最高可达110英里,建成后两地旅行时间最多可节省约90分钟。
北卡罗来纳州交通部表示,项目将修复和改善这条历史铁路走廊,新建轨道、升级既有基础设施,并兼顾货运运行与交通安全,与弗吉尼亚客运铁路管理局等伙伴协调推进。罗利联合车站将增建第二座站台,沿线多处平交道口将改为立交桥。
目前施工首先集中在罗利至韦克森林段:罗利市杜兰特路的平交道口正在改为车辆跨线桥,桥梁主体预计2026年11月完工,其余修复工作将持续至2028年7月;另一处新希望教堂路的2270万美元桥梁工程已于2026年2月开工。2023年获批的10.9亿美元联邦拨款同样用于该段建设。州长 Josh Stein 在10月27日的州交通峰会上提及这笔资金,称其将加强北卡罗来纳州与东北地区的联系。
北卡罗来纳州交通部尚未公布整条走廊的最终完工日期与总造价,首期重点仍是罗利至韦克森林段。
(来源:北卡罗来纳州交通部)
North Carolina S-Line Rail Project Moves Forward With $550 Million in Federal Funding: Raleigh-to-Richmond Corridor Designed for 110 MPH
Raleigh, Wake County, North Carolina — A $550 million grant from the Federal Railroad Administration is moving the S-Line rail project forward: the passenger rail corridor linking Raleigh, North Carolina, with Richmond, Virginia, runs about 162 miles, is designed for speeds of up to 110 mph, and is expected to cut travel time between the two cities by up to about 90 minutes once complete.
The North Carolina Department of Transportation says the project will restore and improve the historic rail corridor, adding new track and upgrading existing infrastructure while accommodating freight operations and traffic safety, in coordination with partners including the Virginia Passenger Rail Authority. Raleigh Union Station will gain a second platform, and several at-grade crossings along the line will be replaced with bridges.
Construction is focused first on the Raleigh-to-Wake Forest segment: the at-grade crossing at Durant Road in Raleigh is being converted into a road bridge over the tracks, with the main structure expected to be completed in November 2026 and remaining restoration work continuing through July 2028. A separate $22.7 million bridge project at New Hope Church Road began in February 2026. A $1.09 billion federal grant approved in 2023 also funds this segment. Governor Josh Stein mentioned the funding at the state transportation summit on October 27, saying it would strengthen North Carolina's links with the Northeast.
NCDOT has not announced a final completion date or total cost for the full corridor; the first phase remains the Raleigh-to-Wake Forest segment.
(Source: North Carolina Department of Transportation)