Pasadena 7318万美元地下电缆更换工程10月19日动工:五英里输电线升级 预计2027年夏完工

Pasadena——位于加州洛杉矶县的Pasadena市,Pasadena 水电局(Pasadena Water and Power, PWP)10月19日启动一项总投资7,318万美元的地下电缆更换工程:更换 Santa Anita 与 Glenarm 两座受电站之间五英里的老旧输电电缆,换装更高容量的新线,为该市2030年实现100%无碳电力的目标升级电网。工程预计2027年夏季完工。
工程预算中,电缆采购占4,395.2万美元;PWP 指出,铜材约占材料成本的75%,而2025年8月1日起实施的50%铜进口关税推高了这部分支出。施工期间,相关线路将停电约六个月,市府将依靠本地发电维持供电,包括 Glenarm 发电厂71兆瓦的 GT-5 机组,预计居民用电服务不会中断。
施工安排方面,施工队工作时间为为工作日上午7时至下午5时、周六上午8时至下午5时,逐段拆除旧缆、敷设新缆。市府提示,施工走廊沿线将有局部交通管制,每个受影响点位的封路一般持续一至两天,居住在 Santa Anita 与 Glenarm 走廊附近的居民需为未来数月间歇性的交通影响预作准备。
PWP 是 Pasadena 市属公用事业,为市内居民与企业提供水电服务。此次更换的输电电缆是该市电网的骨干环节,容量提升后将为未来可再生能源并网与用电增长预留空间。(GSM 据 Pasadena 水电局项目信息)
Pasadena Begins $73.18 Million Underground Cable Replacement on Oct. 19: Five Miles of Lines Upgraded by Summer 2027
PASADENA — Pasadena is a city in Los Angeles County, California. Pasadena Water and Power (PWP) begins work October 19 on a $73.18 million project to replace five miles of aging subtransmission cables between the Santa Anita and Glenarm receiving stations, installing higher-capacity lines to modernize the grid for the city's goal of 100% carbon-free electricity by 2030. Completion is expected in summer 2027.
Cable purchases account for $43.952 million of the budget. PWP notes copper makes up about 75% of those material costs, a figure affected by the 50% federal tariff on copper that took effect August 1, 2025. During the roughly six-month de-energization period, the city will rely on internal generation — including the 71-megawatt GT-5 unit at the Glenarm Power Plant — to maintain service, and no customer outages are anticipated.
Crews will work weekdays from 7 a.m. to 5 p.m. and Saturdays from 8 a.m. to 5 p.m., removing old cables and installing the new lines section by section. Residents should expect localized traffic controls near the construction corridor, with closures at each affected location lasting one to two days.
PWP is Pasadena's community-owned utility, providing water and electricity within the city. The upgraded cables form a backbone of the local grid, adding capacity for future renewable integration and demand growth. (GSM, based on Pasadena Water and Power project information)
发布:GSM·美国(发布链接)
图片来源:图:Pasadena 市政厅(资料图)。图片来源:Wikimedia Commons,公有领域。Photo: Pasadena City Hall (file photo). Source: Wikimedia Commons, Public domain.
GSM Global · 本篇英文版 English edition of this story