Azure能源密西西比州1500兆瓦电厂项目进入市场准备最后阶段

2026-10-23 · 各州 · GSM News

Algorhythm Holdings 公司(纳斯达克代码 RIME)10月23日发布运营进展,披露其旗下 Azure Energy 担任战略顾问的密西西比州1500兆瓦联合发电项目工程已接近完成,正面向数据中心和先进制造企业等潜在租户推介。项目位于密西西比州中北部一处1664英亩地块,采用可再生天然气与生物质联合发电方案。

项目由500兆瓦生物质热解发电、1000兆瓦天然气发电及一座15万吨吸收式冷水厂组成,全部电力以“表后”方式直供单一大型同址租户。项目总投资73.4亿美元,分三期投运:开工通知发出后18个月内首期交付约250兆瓦,54个月内达产;二期工程定于2026年10月完成,独立工程师报告预计12月出炉。

Azure 持有该项目10%股权,预计2027年获约500万美元咨询费。若项目建成投运,Azure 年均息税折旧摊销前利润约4000万美元;若2027年初获最终许可后整体出售,按市况估值最高16.6亿美元,Azure 股权对应约1.66亿美元。公司计划2026年第四季度前选定资本市场合作伙伴,2027年一季度初启动全面推介。

来源:GSM·美国

Azure Energy Prepares 1,500 MW Mississippi Power Project for Market

Algorhythm Holdings, Inc. (NASDAQ: RIME) provided an operational update on October 23 on a 1,500 MW combined renewable natural gas and biomass power project in Mississippi for which its Azure Energy unit serves as strategic advisor. Engineering for the project is nearly complete, and it is being marketed to potential tenants, including data centers and advanced manufacturing facilities that would co-locate on site.

The $7.34 billion project will sit on a 1,664-acre site in north-central Mississippi. It combines 500 MW of biomass pyrolysis-to-power generation, 1,000 MW of natural gas generation and a 150,000-ton absorption chilled water plant, with all output delivered behind the meter to a single co-located large-load tenant. The campus is expected to become operational in three phases, the first delivering about 250 MW within 18 months of notice to proceed and full capacity within 54 months. Phase II engineering is scheduled for completion in October 2026, and the Independent Engineer report is due in December 2026.

Azure holds a 10 percent equity stake and expects about $5 million in fee income in 2027. If completed, the project is projected to earn Azure about $40 million in annual EBITDA; alternatively, it could be sold after final permitting in early 2027 at an estimated value of up to $1.66 billion, putting Azure's stake at about $166 million. The company expects to select capital markets partners before the end of the fourth quarter of 2026, with full marketing expected in early 2027.

Source: GSM·America

来源:GSM·美国(原文链接)

图片来源:图:联合循环发电厂(资料图)。摄影:Doc Searls,CC BY 2.0,经 Wikimedia Commons。 / Photo: a combined-cycle power plant (file photo), by Doc Searls, CC BY 2.0, via Wikimedia Commons.

本频道最新更多 ›

← 返回各州 全部新闻 关于我们

GSM首页白宫联邦加州南加社区各州社会选举世界中国外交城市站国家站宣传司法信仰专题非盈利机构科技金融体育文旅电影音乐演出活动教育医疗生活地产保险娱乐游戏