加州公用事业委员会改划高火险区地图 南加州爱迪生新增47处获准、申请移除61处被否

Sacramento——加州公用事业委员会(CPUC)10月8日在 Sacramento 举行的表决会议上,通过编号 D.26-10-003 的裁定,部分批准 Southern California Edison(南加州爱迪生,SCE)修改其服务区「高火险区」(High Fire-Threat District)边界的申请:新增47处区域列入高火险区获准,申请移除的61处则被否决。委员会同时责成其安全政策处在2027年就高火险区地图的后续修改举行研讨会。
高火险区地图决定了电力公司在相应区域须执行的防火安全规范强度,包括线路巡查、植被清理与设备标准。SCE 的服务区覆盖南加州大片山麓与峡谷地带,本周正值 Norte Fire、Bryson Fire 等多场山火在南加多县燃烧,该地图的划定直接关系当地社区的火灾防控要求。
同场会议还批准了 PG&E 的 Diablo Canyon 核电站延长运营成本决议(第 E-5483 号),核准2023年9月至2025年12月期间12.2亿美元的延运成本;否决 SDG&E 停止运营地区性能效项目的请求;并否决南加州天然气公司为其客户信息系统更换项目追加2,490万美元运维资金的申请。PG&E 为 San Jose 一座250兆瓦 Google 数据中心供电的个案协议则被押后至10月29日会议再议。
信息来源:加州公用事业委员会10月8日表决会议结果(据 Stoel Rives 能源监管简报与 RTO Insider 报道)
CPUC Redraws High Fire-Threat Map: 47 SCE Areas Added, 61 Proposed Removals Denied
SACRAMENTO — At its October 8 voting meeting in Sacramento, the California Public Utilities Commission (CPUC) adopted Decision D.26-10-003, partially granting Southern California Edison's petition to modify the boundaries of the High Fire-Threat District in its service territory: SCE's proposed addition of 47 areas was approved, while its proposed removal of 61 areas was denied. The Commission's Safety Policy Division was directed to hold a workshop in 2027 on future proposed modifications to the fire-threat map.
The High Fire-Threat District map determines the strength of fire-safety regulations utilities must follow in each area, including inspection, vegetation management and equipment standards. SCE's territory covers large foothill and canyon areas of Southern California, and the decision came in a week when the Norte Fire, Bryson Fire and other blazes were burning across several Southern California counties.
At the same meeting, the Commission approved $1.22 billion in Diablo Canyon extended operations costs for PG&E covering September 2023 through December 2025 under Resolution E-5483, denied SDG&E's proposal to discontinue its regional energy efficiency programs, and denied SoCalGas's request for $24.9 million in additional funding for its customer information system replacement. A proposed agreement for PG&E to energize a new 250-megawatt Google data center load in San Jose was held over to the October 29 meeting.
Sources: CPUC October 8 voting meeting results, as summarized by Stoel Rives and reported by RTO Insider.
发布:GSM·美国(发布链接)
图片来源:图:高压输电线路与铁塔(资料照片)。图片来源:Stefan Andrej Shambora,Wikimedia Commons,CC BY 2.0。Photo: High-voltage transmission towers and lines (file photo). Source: Stefan Andrej Shambora, via Wikimedia Commons, CC BY 2.0.
GSM Global · 本篇英文版 English edition of this story