GSM城市站国家站国际

联邦法院批准初步禁令,Revolution Wind海上风电项目可立即复工

2026-01-12 · 各州 · GSM News
联邦法院批准初步禁令,Revolution Wind海上风电项目可立即复工

2026年1月12日,美国哥伦比亚特区联邦地区法院批准海上风电项目 Revolution Wind 寻求的初步禁令,暂缓执行内政部海洋能源管理局(BOEM)2025年12月22日发出的停工令。这个位于罗得岛州与康涅狄格州外海、装机704兆瓦的项目可以立即重启受影响的施工,相关诉讼继续审理。

Revolution Wind 是 Global Infrastructure Partners 旗下 Skyborn Renewables 与 Ørsted 各占一半的合资项目,建成后向罗得岛州与康涅狄格州供电。项目方 Ørsted 在法院裁定后表示,项目将尽快复工,安全是首要考虑,目标是为美国东北部提供可负担、可靠的电力,项目方还将研究如何与美国政府合作,争取一个迅速而持久的解决方案。

这个项目在停工令发出时已完成约87%,65台风机已安装58台。2025年12月22日,内政部以涉密报告提出的国家安全风险为由,一并暂停五个在建大型海上风电项目的租约,Revolution Wind 是其中之一,其他四个项目当时仍处于暂停状态。项目方挑战的是 BOEM 局长2025年8月22日与12月22日发出的两道命令。

据当日庭审报道,主审法官 Royce Lamberth 在法庭上表示,12月22日的停工令看上去不合理、似乎缺乏依据,并指出政府援引的涉密新信息不足以解释为何要让整个项目全面停工。法院的初步禁令只解决停工令在诉讼期间是否执行,不是对案件实体的最终判决。

关联:Revolution Wind 海上风电项目投入商业运营:704兆瓦电力可供35万户家庭

Federal Court Grants Preliminary Injunction, Allowing Revolution Wind to Resume Construction Immediately

On January 12, 2026, the U.S. District Court for the District of Columbia granted the preliminary injunction sought by Revolution Wind, staying the December 22, 2025 suspension order issued by the Department of the Interior's Bureau of Ocean Energy Management (BOEM). The 704-megawatt offshore wind project off Rhode Island and Connecticut may restart impacted construction activities immediately while the underlying lawsuit proceeds.

Revolution Wind is a 50/50 joint venture between Global Infrastructure Partners' Skyborn Renewables and Ørsted, and it will supply power to Rhode Island and Connecticut. Ørsted said after the ruling that the project will resume construction work as soon as possible, with safety as the top priority, to deliver affordable, reliable power to the Northeast, and that it will determine how best to work with the U.S. administration to achieve an expeditious and durable resolution.

The project was about 87 percent complete when the suspension order was issued, with 58 of its 65 turbines installed. On December 22, 2025, the Interior Department paused the leases for all five large-scale offshore wind projects under construction in the United States, citing national security risks identified in classified reports; Revolution Wind was one of the five, and the other four remained paused at the time. The lawsuit challenges BOEM Director's orders issued on August 22, 2025 and December 22, 2025.

According to reports of the hearing, Judge Royce Lamberth said from the bench that the December 22 stop-work order appeared unreasonable and seemingly unjustified, and that the classified information cited by the government did not constitute a sufficient explanation for entirely stopping work on the project. A preliminary injunction decides only whether the order is enforced while the case is pending; it is not a final judgment on the merits.

Related: Revolution Wind Offshore Wind Project Reaches Commercial Operation, Powering 350,000 Homes

来源:Ørsted

发布:GSM·美国(发布链接)

图片来源:图:罗得岛州外海的 Block Island 海上风电场(资料照片),与 Revolution Wind 同属罗得岛外海海上风电项目。美国能源部摄,公共领域,经 Wikimedia Commons。 / Photo: The Block Island Wind Farm off Rhode Island (file photo), an offshore wind project in the same waters as Revolution Wind. Photo by the U.S. Department of Energy, public domain, via Wikimedia Commons.

GSM Global · 本篇英文版 English edition of this story

本频道最新更多 ›

← 返回各州 全部新闻 关于我们