GSM城市站国家站国际

能源部下紧急令,科罗拉多州Craig电站1号燃煤机组延退至2026年3月30日

2025-12-30 · 联邦 · GSM News
能源部下紧急令,科罗拉多州Craig电站1号燃煤机组延退至2026年3月30日

美国能源部2025年12月30日发布第202-25-14号紧急令,要求位于科罗拉多州 Moffat 县 Craig 市的 Craig 电站1号机组在原定退役时间之后继续保持可运行状态,延退至2026年3月30日。这台446.4兆瓦的燃煤机组由 Tri-State 发电与输电协会运营。

能源部在命令中认定,西部电力协调委员会西北评估区存在电力短缺与发电设施短缺等紧急状况,遂依据《联邦电力法》第202(c)条发布此令。命令自美东时间2025年12月30日晚11时59分生效,至2026年3月30日晚11时59分届满;其间 Tri-State 与共同业主 Platte River 电力局、Salt River Project、PacifiCorp 与 Xcel Energy 须与西部地区电力管理局落基山地区及 Southwest Power Pool West 协调,采取一切必要措施确保机组可按调度运行。

Craig 电站共有三台机组:2号机组同为446.4兆瓦,3号机组为534.8兆瓦,两台原计划2028年退役,1号机组则原定2025年12月停止运行。命令还要求 Tri-State 在2026年1月20日前向能源部提交机组相关信息,并明确1号机组在紧急期内不计作容量资源。

Energy Department Orders Colorado's Craig Station Unit 1 to Stay Available Until March 30, 2026

The U.S. Department of Energy on December 30, 2025 issued Emergency Order No. 202-25-14 requiring Unit 1 of the Craig Station in the city of Craig, Moffat County, Colorado, to remain available to operate beyond its planned retirement, through March 30, 2026. The 446.4-megawatt coal-fired unit is operated by the Tri-State Generation and Transmission Association.

In the order, the Department determined that an emergency exists within the Western Electricity Coordinating Council Northwest assessment area due to a shortage of electric energy and a shortage of generation facilities, and issued the order under section 202(c) of the Federal Power Act. Effective at 11:59 p.m. Eastern time on December 30, 2025 and expiring at 11:59 p.m. Eastern time on March 30, 2026, the order directs Tri-State and the co-owners, Platte River Power Authority, Salt River Project, PacifiCorp and Xcel Energy, in coordination with the Western Area Power Administration Rocky Mountain Region and Southwest Power Pool West, to take all measures necessary to ensure the unit is available to operate.

Craig Station has three units in all: Unit 2 is also rated at 446.4 megawatts and Unit 3 at 534.8 megawatts, and both are slated to retire in 2028, while Unit 1 had been scheduled to cease operations in December 2025. The order also directs Tri-State to provide the Department with information about the unit by January 20, 2026, and provides that Unit 1 shall not be considered a capacity resource during the emergency period.

来源:美国能源部

发布:GSM·美国(发布链接)

图片来源:图:位于华盛顿的美国能源部总部福雷斯特尔大楼(资料照片)。Tim Evanson 摄,CC BY-SA 2.0,经 Wikimedia Commons;联邦固定图库同源图。 / Photo: The James Forrestal Building, headquarters of the U.S. Department of Energy in Washington (file photo). By Tim Evanson, CC BY-SA 2.0, via Wikimedia Commons; federal fixed image library image.

GSM Global · 本篇英文版 English edition of this story

本频道最新更多 ›

← 返回联邦 全部新闻 关于我们

GSM首页白宫联邦加州南加各州社会军事司法选举世界中国城市站国家站移民宣传专题视频直播放映厅电子书电子报科技金融教育医疗影视音乐体育文旅时尚演出活动娱乐游戏生活美食户外交通汽车地产保险儿童长者留学生宠物信仰非盈利机构