波士顿市绿线信号现代化提速:新信号缆已铺40英里,三大枢纽站改造超九成

2026-10-07 · 城市 · GSM News

波士顿市地铁绿线的百年信号系统现代化正在提速。MBTA 10月5日通报,经过连续9天隧道全天候施工,全线72英里新信号缆已铺设40英里,129个新信号接线箱(替换1940年代旧件)安装超过85%;Copley、Park Street、Government Center 三大枢纽站改造进度分别达100%、98%与95%。新系统将升级轨道电路,并为明年投入的新车做准备,提升班次密度与准点率。(GSM 据 MBTA 官方通报摘编)

Boston's Green Line signal modernization advances: 40 miles of new cable in, hub stations over 90% complete

Boston's century-old Green Line signal system is getting a modern overhaul. The MBTA said Oct. 5 that after nine straight days of around-the-clock tunnel work, crews have installed 40 of 72 planned miles of new signal cable and more than 85% of 129 new signal bungalows replacing 1940s equipment; the Copley, Park Street and Government Center hub stations stand at 100%, 98% and 95% complete. The project readies the line for new Type 10 trains next year. (GSM, from the MBTA release)